Ajoya Cabanatuan Construction Updates Q4 2020

Feb 21, 2021

Site Development Site development is nearing its completion at 85% with a target completion date within the first quarter of this year. House Construction Construction is well underway for 31 units, with 98 more units targeted to begin with the year. Vecino Turnovers Turnovers are set to start in Q3 of this year. Sales A… View Article

Read More

The Villages at Lipa Construction Updates Q4 2020

Feb 21, 2021

Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year. House construction is scheduled to begin this first quarter. All five model units in the Model Village… View Article

Read More
×