House Construction
We are pleased to update you that your community is taking shape with 20 houses underway.
Site Development
We’re at a 73% completion rate for site development. Construction works will resume once enhanced community quarantine (ECQ) is lifted. The target completion date is in the second half of 2020.
Amenities
Offering generous spaces for family fun, Ajoya Cabanatuan’s amenities are underway. Expect to fully enjoy and experience the clubhouse, court, swimming pool, and pool pavilion by the fourth quarter of 2021.
Constructions are in full swing 96 houses in Brook and 55 houses in Sierra are currently under construction. Turnovers to the vecinos are expected to begin Q3 2022. Site Development Brook is at 69.2% completed, while Sierra is at 72.4% completed. The spine road in Malvar Exit still has 75 meters to go before completion…. View Article
Read MoreHOUSE CONSTRUCTION All 67 houses in Phase 2 are 100% constructed. LANDSCAPING AND AMENITIES Landscaping in Phase 2 is now completed, while construction of permanent fences is set to begin in Q3 of this year. TURNOVERS Turnovers for units and lots are still ongoing. VALUE APPRECIATION A Pristina North Residences 2 unit now starts at… View Article