While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year.
There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022.
The model units also remain open for vecinos who want to visit the site. Our Property Specialists and/or Accredited Brokers will be able to assist you on scheduling visits.
Main amenities are targeted to be completed by Q4 this year.
House turnovers are scheduled to begin in Q3 this year.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click here to share your feedback with us.
Wrapping up the site development for the Light Phase, its guardhouse is set to be completed within the first quarter of this year. The Foressa Lodge receives its green light to start construction in the first half of the year. The sanctuary you have long deserved is here. Turnovers are scheduled to begin in the… View Article
Read MorePOST-TYPHOON ODETTE RECOVERY EFFORTS We are committed to ensuring that Pristina North vecinos and your properties are being well-taken care of especially during these trying times. Below are the site updates after Typhoon Odette hit the community, along with the rest of Visayas and Mindanao, last December: Water and power supply are fully restored as… View Article
Read MoreP 0 / month