While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year.
There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022.
The model units also remain open for vecinos who want to visit the site. Our Property Specialists and/or Accredited Brokers will be able to assist you on scheduling visits.
Main amenities are targeted to be completed by Q4 this year.
House turnovers are scheduled to begin in Q3 this year.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click here to share your feedback with us.
TURNOVERS A total of 149 houses and 41 residential lots have been successfully turned over as of Q3 2021. Due for a home loan take out? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 427 houses have been constructed to date while the construction of 267 houses is in… View Article
Read MoreHOUSE CONSTRUCTION All 67 houses in Phase 2 are 100% constructed. LANDSCAPING AND AMENITIES Landscaping in Phase 2 is now completed, while construction of permanent fences is set to begin in Q3 of this year. TURNOVERS Turnovers for units and lots are still ongoing. VALUE APPRECIATION A Pristina North Residences 2 unit now starts at… View Article
Read MoreP 0 / month