74.26% of construction completed.
Target completion in Q1 2021.
17 houses under construction, 1 bare model unit completed, 2 model units for Interior Design fit-out scheduled to open early Q4 2020.
Clubhouse, Court, Pool Pavilion and Pool target completion: 2nd half of 2021
Phase 1A opened in May 2018
SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article