74.26% of construction completed.
Target completion in Q1 2021.
17 houses under construction, 1 bare model unit completed, 2 model units for Interior Design fit-out scheduled to open early Q4 2020.
Clubhouse, Court, Pool Pavilion and Pool target completion: 2nd half of 2021
Phase 1A opened in May 2018
Site Development Site development is nearing its completion at 85% with a target completion date within the first quarter of this year. House Construction Construction is well underway for 31 units, with 98 more units targeted to begin with the year. Vecino Turnovers Turnovers are set to start in Q3 of this year. Sales A… View Article