74.26% of construction completed.
Target completion in Q1 2021.
17 houses under construction, 1 bare model unit completed, 2 model units for Interior Design fit-out scheduled to open early Q4 2020.
Clubhouse, Court, Pool Pavilion and Pool target completion: 2nd half of 2021
Phase 1A opened in May 2018
Construction is in full swing Brook Village currently has 267 houses under construction and 80 completed houses. Meanwhile, Sierra Village has 203 houses under construction and 37 completed houses. Site Development Site development of Brook Village is at 96.06% completion, Sierra Village is at 96.09% completion, while Meadow Village is at 17.21% completion. Amenities Main… View Article
Read MoreConstruction is making steady headway 232 house and lot units have been completed while 164 houses are under construction. 3 villas have been completed while 5 villas are ongoing construction. Site Development is 100% complete Amenities The clubhouse, pool, boardwalk, jogging path at the lagoon, and other amenities are operational. The construction of the Crest… View Article
Read MorePhase Light 1A land development is fully completed, while Phase Light 1A site development is 93% complete, with a target completion in Q1 2025. Phase Light 1B land development is 99% complete, with a target completion in Q1 2024, while Phase Light 1B site development is 77% complete, with a target completion in Q2 2025…. View Article