Ongoing construction at 79% completion.
Target completion in Q1 2021.
17 houses ongoing construction.
Model Units now open.
Ongoing construction of Clubhouse, Court, Pool Pavilion, and Facilities.
Target completion in Q4 2021.
Projected to start in Q1 2021.
New inventory for lots opened for sale due to demand.
TURNOVERS Priveya Hills has welcomed its new batch of vecinos with 123 residential lots turned over. CONSTRUCTION AND LAUNCHED PHASES Two vecinos have moved in, while the construction for eight houses is ongoing and in full swing. The construction for 8 houses are ongoing and in full swing Phases 1, 2, 3, and 5A are… View Article
Read MoreHouse Construction The model units and 169 houses have been completed, while the construction of 72 house units are ongoing and in full swing. Land Development is fully completed. Amenities The Gate Guardhouse, Basketball Court, and Boulevard Landscape has been completed. The Clubhouse is set for completion by Q2 2023, while the Pool and Playground… View Article
Read MoreACCEPTANCE Acceptance for both residential lots and houses are set to commence in Q4 2021. Need assistance in funding your dream home in Ajoya Cabanatuan? Read more about our home loan offerings and services through this LINK. HOUSE AND SHOPHOUSE CONSTRUCTION With 24 houses already completed, the construction of 136 houses and shophouses are in full… View Article
Read MoreP 0 / month