Construction Updates

Suggested Articles

Ajoya Capas Construction Updates Q3 2023

Oct 25, 2023

House Construction The model units and 159 houses have been completed, while the construction of 39 house units are ongoing and in full swing. Site Development is fully completed Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 61 units have been turned over…. View Article

Read More

The Villages at Lipa Construction Updates Q2 2022

Sep 27, 2022

TURNOVERS EXPECTED TO START IN Q3 2022. HOUSE CONSTRUCTION IN FULL SWING. There are currently 213 houses under construction and 18 completed houses in Brook Village. In Sierra Village, there are 9 completed houses and 72 houses currently under construction. SITE DEVELOPMENT Site development of Brook Village is at 80.32% completion, while Sierra Village is… View Article

Read More
×