We are pleased to update you that your community is taking shape with 48 houses underway.
Site Development
We’re at a 99% completion rate for site development. Construction works will resume once enhanced community quarantine (ECQ) is lifted. The target completion date is in the second quarter of 2020.
Amenities
Offering generous spaces for family fun, Ajoya Capas’ amenities are underway. The clubhouse is at a 4% completion rate. Expect to fully enjoy and experience the clubhouse, court, and swimming pool by the fourth quarter of 2021.
Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 84% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is currently at 91% completion, with the structure’s target completion set for Q3 2023. The Phase 1A Streetscape and main entry signage is ongoing… View Article