House Construction
We are pleased to update you that your community is taking shape with 48 houses underway.
Site Development
We’re at a 99% completion rate for site development. Construction works will resume once enhanced community quarantine (ECQ) is lifted. The target completion date is in the second quarter of 2020.
Amenities
Offering generous spaces for family fun, Ajoya Capas’ amenities are underway. The clubhouse is at a 4% completion rate. Expect to fully enjoy and experience the clubhouse, court, and swimming pool by the fourth quarter of 2021.
TURNOVERS 22 house units have been turned over. HOUSE CONSTRUCTION 127 houses have been constructed along with the model units, while the construction of 40 house units are ongoing and in full swing. AMENITIES The gate, guardhouse, pool, clubhouse, boulevard landscape, and playground have been completed, while the basketball court is set to be completed… View Article
Read MoreACCEPTANCE Acceptance for both residential lots and houses are set to commence in Q4 2021. Need assistance in funding your dream home in Ajoya Cabanatuan? Read more about our home loan offerings and services through this LINK. HOUSE AND SHOPHOUSE CONSTRUCTION With 24 houses already completed, the construction of 136 houses and shophouses are in full… View Article
Read MoreTURNOVERS The first batch of turnovers commenced in Q1 2022, with 4 houses turned over. Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 93 house units have been constructed, as well as the model units while 54 house units and shophouses are… View Article
Read MoreP 0 / month