The Villages at Lipa Q3 2021 Construction Updates

Nov 11, 2021

CONSTRUCTION Construction of the spine road to Malvar Entrance is now at 87% completion. SITE VISITS The Villages at Lipa remains open for site visits and model village viewing. Book a visit with your Property Specialist or Broker today. Rest assured that IATF’s guidelines are strictly implemented within its premises. VALUE APPRECIATION Lot value in… View Article

Read More

The Villages at Lipa Construction Updates Q4 2020

Feb 21, 2021

Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year. House construction is scheduled to begin this first quarter. All five model units in the Model Village… View Article

Read More

Ajoya Pampanga Construction Update Q1 2021

Jun 18, 2021

SITE DEVELOPMENT Site development is at 54%, with Phase 1 (64 hectares) set to be completed by November 2021. HOUSE CONSTRUCTION House construction began with 20 units in January. Construction of the model units is also in full swing, targeted to be completed by Q4 this year. AMENITIES Main amenities are targeted to be completed… View Article

Read More
×