Ongoing construction at 84% completion.
Target completion in the last quarter of 2020.
54 houses ongoing construction.
Model Units to be opened in December 2020.
Ongoing construction of Clubhouse, Court, Pool Pavilion, and Facilities.
Target completion in Q4 2021.
Projected to start in Q1 2021.
New inventory for lots opened for sale due to demand.
SITE DEVELOPMENT Site development both for the Sierra and Brook Villages are at 28% and 30% completion respectively. HOUSE CONSTRUCTION Excavations for house construction in both villages began in Q1. Vecinos can now also expect model units to be available for viewing by July this year. VALUE APPRECIATION Investments in The Villages at Lipa are… View Article
Read MoreTURNOVERS 25 residential units have been turned over in Pristina North Residences Phase 2 as of Q1 2022. AMENITIES Street names and signages in Pristina North Residences 2 are set to be installed by Q2 2022. Meanwhile, the construction of the perimeter fence in on going and set to be completed by Q3 2022. VALUE… View Article
Read MoreP 0 / month