Construction Updates

Suggested Articles

Ajoya Capas Construction Update Q1 2021

May 31, 2021

HOUSE CONSTRUCTION 30 houses are completed while construction for 106 new units is in full swing. The model units also remain open for vecinos who want to visit the site. Our Property Specialists and/or Accredited Brokers will be able to assist you in scheduling visits. AMENITIES The Clubhouse, Court, and Pool Facilities are all under… View Article

Read More

Ajoya Cabanatuan Construction Update Q1 2021

Jun 8, 2021

SITE DEVELOPMENT While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year. HOUSE CONSTRUCTION There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022. The model units also remain… View Article

Read More

Priveya Hills Construction Update Q1 2021

Jun 8, 2021

SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article

Read More
×