Site development is now 100% complete. All roads within the property are passable.
Construction is well underway for 65 units, with 53 more units targeted to begin within the year.
The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021.
Turnovers are set to begin in Q2 2021.
SITE DEVELOPMENT While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year. HOUSE CONSTRUCTION There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022. The model units also remain… View Article