Site development is now 100% complete. All roads within the property are passable.
Construction is well underway for 65 units, with 53 more units targeted to begin within the year.
The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021.
Turnovers are set to begin in Q2 2021.
ACCEPTANCE Acceptance for residential lots is ongoing while turnovers are set to commence in Q1 2022. Need assistance in funding your dream home in Ajoya Pampanga? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION AND AMENITIES We are pleased to inform you that the construction of 60 units and… View Article
Read MoreTURNOVERS First batch of property turnovers is set to commence in Q1 2022. Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Our Construction Team has completed 70 house units while 49 more units are under construction. AMENITIES The main amenities at… View Article
Read MoreP 0 / month