Construction Updates

Suggested Articles

Foressa Mountain Town Construction Updates Q2 2023

Sep 15, 2023

Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 84% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is currently at 91% completion, with the structure’s target completion set for Q3 2023. The Phase 1A Streetscape and main entry signage is ongoing… View Article

Read More

Ajoya Capas Construction Updates Q1 2022

Jun 18, 2022

TURNOVERS The first batch of turnovers commenced in Q1 2022, with 4 houses turned over.  Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 93 house units have been constructed, as well as the model units while 54 house units and shophouses are… View Article

Read More

Ajoya Capas Construction Updates Q3 2022

Nov 29, 2022

TURNOVERS 22 house units have been turned over. HOUSE CONSTRUCTION 127 houses have been constructed along with the model units, while the construction of 40 house units are ongoing and in full swing. AMENITIES The gate, guardhouse, pool, clubhouse, boulevard landscape, and playground have been completed, while the basketball court is set to be completed… View Article

Read More
×