Site Development
We are pleased to update you that your community is taking shape. Site development for Phase 1 started last March. Construction works will resume once enhanced community quarantine (ECQ) is lifted. The target completion date for Phase 1 is in August 2020.
Construction is in full swing Brook Village currently has 267 houses under construction and 80 completed houses. Meanwhile, Sierra Village has 203 houses under construction and 37 completed houses. Site Development Site development of Brook Village is at 96.06% completion, Sierra Village is at 96.09% completion, while Meadow Village is at 17.21% completion. Amenities Main… View Article
Read MoreTURNOVERS Priveya Hills has welcomed its new batch of vecinos with 123 residential lots turned over. CONSTRUCTION AND LAUNCHED PHASES Two vecinos have moved in, while the construction for ten houses is ongoing and in full swing. Land development of Phases 1, 2, 3, and 5A is 100% complete. AMENITIES The target completion of the… View Article