Site development is at 54%, with Phase 1 (64 hectares) set to be completed by November 2021.
House construction began with 20 units in January. Construction of the model units is also in full swing, targeted to be completed by Q4 this year.
Main amenities are targeted to be completed by Q1 2022.
Turnover of lots are set to begin in Q1 2022, while houses are scheduled for Q2 2022.
An Ajoya Pampanga lot now starts at Php10,600 per square, an increase from its launch price of Php8,900 per square in 2019.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click HERE to share your feedback.
Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year. House construction is scheduled to begin this first quarter. All five model units in the Model Village… View Article
Read MoreSITE DEVELOPMENT Site development both for the Sierra and Brook Villages are at 28% and 30% completion respectively. HOUSE CONSTRUCTION Excavations for house construction in both villages began in Q1. Vecinos can now also expect model units to be available for viewing by July this year. VALUE APPRECIATION Investments in The Villages at Lipa are… View Article
Read MoreP 0 / month