Site development is at 54%, with Phase 1 (64 hectares) set to be completed by November 2021.
House construction began with 20 units in January. Construction of the model units is also in full swing, targeted to be completed by Q4 this year.
Main amenities are targeted to be completed by Q1 2022.
Turnover of lots are set to begin in Q1 2022, while houses are scheduled for Q2 2022.
An Ajoya Pampanga lot now starts at Php10,600 per square, an increase from its launch price of Php8,900 per square in 2019.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click HERE to share your feedback.
House Construction 5 houses have been built, with vecinos already moved in. 7 houses are currently under construction. Site Development Land development of launched Phases 1, 2, 3, and 5A are 100% complete. Amenities The Clubhouse has reached 84% completion, with the structure expected to be finished by Q4 2023. The development of North Park,… View Article
Read MoreWrapping up the site development for the Light Phase, its guardhouse is set to be completed within the first quarter of this year. The Foressa Lodge receives its green light to start construction in the first half of the year. The sanctuary you have long deserved is here. Turnovers are scheduled to begin in the… View Article
Read MoreP 0 / month