Seafront Residences Construction Updates Q1 2022

Jun 20, 2022

TURNOVERS ARE FULLY UNDERWAY Seafront Residences has turned over 94 houses and lots and 37 lot only properties. A new building of Seafront Villas was opened last March 2022. Seafront Crest vecinos who are planning to build their home may visit the Property Management Office for Construction Guidelines. SEAFRONT VILLAS SOON TO BE READY FOR… View Article

Read More

Seafront Residences Construction Updates Q3 2023

Oct 25, 2023

Construction is making steady headway 232 house and lot units have been completed while 164 houses are under construction. 3 villas have been completed while 5 villas are ongoing construction. Site Development is 100% complete Amenities The clubhouse, pool, boardwalk, jogging path at the lagoon, and other amenities are operational. The construction of the Crest… View Article

Read More

Priveya Hills Construction Updates Q3 2021

Nov 11, 2021

AMENITIES The Clubhouse is set to be finished by Q3 2022. Meanwhile, botanicals have been planted along the spine road and around the clubhouse to give ample shade and protection from extreme heat. SALES An exclusive discount of up to Php 5.3M* on prime lots awaits for spot cash purchases. This promo runs until December… View Article

Read More
×