Ongoing construction at 20% completion.
Target completion in the first half of 2021.
Construction of Model Units to start in Q1 2021.
Projected to start in Q3 2021.
Phase Light 1A land development is fully completed, while Phase Light 1A site development is 93% complete, with a target completion in Q1 2025. Phase Light 1B land development is 99% complete, with a target completion in Q1 2024, while Phase Light 1B site development is 77% complete, with a target completion in Q2 2025…. View Article
Read MoreHouse Construction 5 houses have been built, with vecinos already moved in. 7 houses are currently under construction. Site Development Land development of launched Phases 1, 2, 3, and 5A are 100% complete. Amenities The Clubhouse has reached 99% completion, with the structure expected to be finished by Q2 2024. The development of North Park,… View Article
Read MoreP 0 / month