Priveya Hills Construction Update Q1 2021

Jun 8, 2021

SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article

Read More

Ajoya Capas Construction Updates Q1 2022

Jun 18, 2022

TURNOVERS The first batch of turnovers commenced in Q1 2022, with 4 houses turned over.  Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 93 house units have been constructed, as well as the model units while 54 house units and shophouses are… View Article

Read More
×