Ajoya Capas Construction Updates Q4 2020

Feb 21, 2021

Site Development Site development is now 100% complete. All roads within the property are passable. House Construction Construction is well underway for 65 units, with 53 more units targeted to begin within the year. Amenities The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021…. View Article

Read More

Ajoya Cabanatuan Construction Updates Q3 2021

Nov 11, 2021

ACCEPTANCE Acceptance for both residential lots and houses are set to commence in Q4 2021. Need assistance in funding your dream home in Ajoya Cabanatuan? Read more about our home loan offerings and services through this LINK. HOUSE AND SHOPHOUSE CONSTRUCTION With 24 houses already completed, the construction of 136 houses and shophouses are in full… View Article

Read More
×