Completed for all launched enclaves.
232 houses completed.
243 houses ongoing construction.
Clubhouse structure, pool facilities, function area, grand lawn, and basketball court are all completed.
Turnovers continued this quarter with 51 houses and 9 lots.
New inventory of 2-storey units were opened in October 2020 due to high demand.
TURNOVERS Property turnovers are set to commence in Q4 2022. Are you in search of funding for your Ajoya Property? Click here to learn more about our home loan options and services. HOUSE CONSTRUCTION 37 houses have been constructed including the model houses, while the construction of 190 house units are ongoing and in full… View Article
Read MoreHOUSE CONSTRUCTION All 67 houses in Phase 2 are 100% constructed. LANDSCAPING AND AMENITIES Landscaping in Phase 2 is now completed, while construction of permanent fences is set to begin in Q3 of this year. TURNOVERS Turnovers for units and lots are still ongoing. VALUE APPRECIATION A Pristina North Residences 2 unit now starts at… View Article