Completed for all launched enclaves.
232 houses completed.
243 houses ongoing construction.
Clubhouse structure, pool facilities, function area, grand lawn, and basketball court are all completed.
Turnovers continued this quarter with 51 houses and 9 lots.
New inventory of 2-storey units were opened in October 2020 due to high demand.
SITE DEVELOPMENT Site development for the Light Phase 1A is now complete with its main guardhouse fully constructed. AMENITIES Construction for the Foressa Lodge will begin in June 2021. VECINO TURNOVER Lot turnovers are rescheduled to begin in Q4 this year to allow the completion of necessary documents that were affected by the community quarantines… View Article
Read MoreTURNOVERS 26 residential units have been turned over in Pristina North Residences Phase 2. HOUSE CONSTRUCTION IS 100% COMPLETED IN Pristina North Residences Phase 2. AMENITIES Street names and signages in Pristina North Residences 2 have been installed as of August 2022. Meanwhile, the construction of the perimeter fence is ongoing and set to be… View Article
Read MoreTURNOVERS 280 house units have been turned over along with 63 residential lots. Are you in search of funding for your Ajoya Property? Click here to learn more about our home loan options and services. HOUSE CONSTRUCTION 562 house units have been completed, while the construction of 296 house units are ongoing and in full… View Article