Construction Updates

Suggested Articles

Foressa Mountain Town Construction Updates Q3 2023

Oct 25, 2023

Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023. The Phase 1A Streetscape and main entry signage are currently… View Article

Read More

Priveya Hills Construction Update Q1 2021

Jun 8, 2021

SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article

Read More
×