Amoa Construction Updates Q2 2020

House Construction: 178 houses completed282 houses under construction Site Development: Complete for all launched enclaves Amenities: 3 swimming pools, clubhouse structure and function areas have been completedGrand lawn and basketball court will be completed by Q3 2020 Vecino Turnovers: 31 houses and 8 lots turned over, turnovers have resumed since lockdown Sales: 15 units of… View Article

By Irish Erika Rodriguez

Copy_of_815x543_News_ALand__7_

Priveya Hills Construction Updates Q2 2020

Site Development: Phase 1 – 100%; Phase 2 – 100%Phase 3 – 99.13%; Phase 5A – 97.57% Amenities: Parks – start of construction: November 2020Pool and Admin Office – operational by Q4 2020 Vecino Turnovers: 116/286 (40%) sold lots turned over, 1 house complete,1 on-going construction, 2 units submitted for approval Available Lots: 20 lots… View Article

By Irish Erika Rodriguez

Copy of 815x543 News ALand (3)

Foressa Mountain Town Construction Update Q2 2020

Site Development: Phase Light A ongoing, site works target completion – Q3 2020. Amenities: Clubhouse and Destination Cafe start of construction – 1st half of 2021. Vecino Turnovers: Will start in Q4 2020

By Irish Erika Rodriguez

Copy of 815x543 News ALand (4)

Pristina North Residences Construction Updates Q2 2020

House Construction: PNR1 – 28/28 (100%) completed PNR 2 – 57/67 (85%) of released houses completed Total – 85/95 (89%) completed Vecino Turnovers: PNR 1 – 89%PNR 2 – 18% Available Units: 3 units – Pristina North Residences (Average TCP = P14M24 units to be opened up within 20204 lots available for sale – Pristina… View Article

By Irish Erika Rodriguez