Site development for the Light Phase 1A is now complete with its main guardhouse fully constructed.
Construction for the Foressa Lodge will begin in June 2021.
Lot turnovers are rescheduled to begin in Q4 this year to allow the completion of necessary documents that were affected by the community quarantines imposed to prevent the spread of COVID-19. Our Customer Service Management Team will be getting in touch with you soon for scheduling matters.
A Foressa lot now starts at Php12,360 per sqm compared to when it was launched in 2017 at Php9,520 per sqm.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click HERE to share your feedback.
SITE DEVELOPMENT Land development of Phase 1A is 100% complete, while Phase 1B is at 29% progress ahead of schedule. AMENITIES Main Pavilion and Main Entry Signage target completion by Q2 2023. VALUE APPRECIATION Residential lots investments at Foressa Mountain Town are enjoying 92% value appreciation. Priced at Php 7,300 per sqm during its launch… View Article
Read MoreSITE DEVELOPMENT Site development has been completed for all the launched phases. AMENITIES Construction of the Clubhouse is in full swing and is expected to be finished by Q2 of 2022. Landscaping of spine road and clubhouse is now ongoing. TURNOVERS One hundred twenty lots have been turned over to the vecinos. Six households are… View Article