Construction Updates

Suggested Articles

Priveya Hills Construction Updates Q3 2023

Oct 25, 2023

House Construction 5 houses have been built, with vecinos already moved in. 7 houses are currently under construction. Site Development Land development of launched Phases 1, 2, 3, and 5A are 100% complete. Amenities The Clubhouse has reached 84% completion, with the structure expected to be finished by Q4 2023. The development of North Park,… View Article

Read More

Ajoya Capas Construction Updates Q1 2023

Mar 31, 2023

House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over…. View Article

Read More

Ajoya Capas Construction Updates Q4 2021

Jan 31, 2022

TURNOVERS First batch of property turnovers is set to commence in Q1 2022. Need assistance in funding your Ajoya Capas property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Our Construction Team has completed 70 house units while 49 more units are under construction. AMENITIES The main amenities at… View Article

Read More
×