Ajoya Capas Construction Updates Q1 2024

Mar 31, 2024

House Construction 188 houses have been completed, while the construction of 45 house units are ongoing and in full swing. Site Development is fully completed Amenities The Clubhouse, Pool, Playground, Basketball Court, Gate Guardhouse, and Boulevard Landscape have been completed. The Town Plaza is set to be completed by Q4 2024. Turnovers 97 units have… View Article

Read More

The Villages at Lipa Construction Updates Q3 2022

Nov 29, 2022

Turnovers expected to start in Q4 2022 Construction is in full swing There are currently 320 houses under construction and 17 completed houses in Brook Village. ┬áIn Sierra Village, there are 26 completed houses and 207 houses currently under construction. Site Development Site development of Brook Village is at 92.24% completion, while Sierra Village is… View Article

Read More
×