The promise of seeing how the Light Phase catches the first glint of the sun each day is becoming a reality. Site Development is now complete as of October 2020.
The community’s main pavilion, the Foressa Lodge, is set to start construction in the first half of 2021. Simultaneously, the Destination Cafe is also set to start construction to become the next hangout spot in the vicinity.
We can’t wait for you to create lasting memories with your family and friends. Turnovers are set to start in the first quarter of next year.
SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article
Read MoreTURNOVERS A total of 149 houses and 41 residential lots have been successfully turned over as of Q3 2021. Due for a home loan take out? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 427 houses have been constructed to date while the construction of 267 houses is in… View Article