The promise of seeing how the Light Phase catches the first glint of the sun each day is becoming a reality. Site Development is now complete as of October 2020.
The community’s main pavilion, the Foressa Lodge, is set to start construction in the first half of 2021. Simultaneously, the Destination Cafe is also set to start construction to become the next hangout spot in the vicinity.
We can’t wait for you to create lasting memories with your family and friends. Turnovers are set to start in the first quarter of next year.
HOUSE CONSTRUCTION We are pleased to announce that 380 houses are now built and completed while the construction of 279 new units is in full blast. AMENITIES Our key amenities including the playground are open for vecinos’ enjoyment with the use of the swimming pools limited per day. Kindly contact your Property Administration to make… View Article
Read MoreHOUSE CONSTRUCTION All 67 houses in Phase 2 are 100% constructed. LANDSCAPING AND AMENITIES Landscaping in Phase 2 is now completed, while construction of permanent fences is set to begin in Q3 of this year. TURNOVERS Turnovers for units and lots are still ongoing. VALUE APPRECIATION A Pristina North Residences 2 unit now starts at… View Article
Read MoreHouse Construction The model units and 173 houses have been completed, while the construction of 25 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Town Plaza is set to launch in… View Article