Construction Updates

Suggested Articles

Ajoya Capas Construction Updates Q1 2023

Mar 31, 2023

House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over…. View Article

Read More

Ajoya Pampanga Construction Updates Q2 2022

Oct 3, 2022

TURNOVERS Property turnovers are set to commence in Q4 2022. Are you in search of funding for your Ajoya Property? Click here to learn more about our home loan options and services. HOUSE CONSTRUCTION 19 house units including the model houses have been constructed, while the construction of 132 house units are ongoing and in… View Article

Read More

Foressa Construction Updates Q1 2022

Jun 27, 2022

TURNOVERS 16 residential lots have been turned over as of Q1 2022.  SITE DEVELOPMENT Site development of Phase 1A is 100% complete.  CEBECO electrical distribution line setup is at 100%.  Streetlights to be installed in 2022 AMENITIES Foressa Lodge is under construction. Meanwhile, pool construction, parks and landscaping of other areas, town center and main… View Article

Read More
×