Site Development
We are pleased to update you on the progress of your sanctuary. 82 residences out of the 95 house inventory have been completed.
Amenities
Your family may now experience endless leisure from the completed amenities in the neighborhood.
Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023. The Phase 1A Streetscape and main entry signage are currently… View Article
Read MoreSITE DEVELOPMENT Land development of Phase 1A is 100% complete, while Phase 1B is at 29% progress ahead of schedule. AMENITIES Main Pavilion and Main Entry Signage target completion by Q2 2023. VALUE APPRECIATION Residential lots investments at Foressa Mountain Town are enjoying 92% value appreciation. Priced at Php 7,300 per sqm during its launch… View Article
Read MoreSite Development Site development is now 100% complete. All roads within the property are passable. House Construction Construction is well underway for 65 units, with 53 more units targeted to begin within the year. Amenities The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021…. View Article
Read MoreP 0 / month