PNR1 – 28/28 (100%) completed
PNR 2 – 57/67 (85%) of released houses completed
Total – 85/95 (89%) completed
PNR 1 – 89%
PNR 2 – 18%
3 units – Pristina North Residences (Average TCP = P14M
24 units to be opened up within 2020
4 lots available for sale – Pristina North Main
6%
Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 84% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is currently at 91% completion, with the structure’s target completion set for Q3 2023. The Phase 1A Streetscape and main entry signage is ongoing… View Article
Read MoreTURNOVERS First batch of property turnovers is set to commence in Q3 2022.Need assistance in funding your Ajoya Property? Read more about our home loan offerings and services through this LINK. CONSTRUCTION AND AMENITIES 4 house units, the guardhouse gate and the boulevard landscape are all completed, while the construction of 124 house units are… View Article
Read MoreP 0 / month