PNR1 – 28/28 (100%) completed
PNR 2 – 57/67 (85%) of released houses completed
Total – 85/95 (89%) completed
PNR 1 – 89%
PNR 2 – 18%
3 units – Pristina North Residences (Average TCP = P14M
24 units to be opened up within 2020
4 lots available for sale – Pristina North Main
6%
SITE DEVELOPMENT While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year. HOUSE CONSTRUCTION There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022. The model units also remain… View Article