Amoa Construction Updates Q4 2020

Feb 22, 2021

Value Appreciation The current lot price has increased to Php16,000/sqm. to date, from Php5,000/sqm. when it was first launched in 2015. House Construction 293 houses are completed while construction for 226 new houses carry on in full swing. Amenities The Central Park facilities remain available for vecinos’ use with health and safety guidelines implemented. Swimming… View Article

Read More

The Villages at Lipa Construction Updates Q1 2022

Jun 27, 2022

Constructions are in full swing 96 houses in Brook and 55 houses in Sierra are currently under construction. Turnovers to the vecinos are expected to begin Q3 2022. Site Development Brook is at 69.2% completed, while Sierra is at 72.4% completed. The spine road in Malvar Exit still has 75 meters to go before completion…. View Article

Read More
×