Site Development
We are pleased to update you on the progress of your neighborhood. Phases 1 and 2 are fully finished. Phases 3 and 5 are at 99.13% and 97.57% completion rates, respectively.
Amenities
With an address of luxurious stature, expect the equally polished parks and clubhouse ready for your enjoyment by December 2020.
TURNOVERS First batch of property turnovers is set to commence in Q1 2022. Need assistance in funding your Ajoya Cabanatuan property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Our Construction Team has completed 24 house units while 179 other units are under construction. AMENITIES The main amenities at… View Article