Phase 1 – 100%; Phase 2 – 100%
Phase 3 – 99.13%; Phase 5A – 97.57%
Parks – start of construction: November 2020
Pool and Admin Office – operational by Q4 2020
116/286 (40%) sold lots turned over, 1 house complete,
1 on-going construction, 2 units submitted for approval
20 lots available at Php 28k/sqm VAT inc.
House Construction The model units and 169 houses have been completed, while the construction of 72 house units are ongoing and in full swing. Land Development is fully completed. Amenities The Gate Guardhouse, Basketball Court, and Boulevard Landscape has been completed. The Clubhouse is set for completion by Q2 2023, while the Pool and Playground… View Article
Read MoreHouse Construction The model units and 90 houses have been completed, while the construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Turnovers 9 units have been turned over. Turnover Offices… View Article
Read MoreP 0 / month