Priveya Hills Construction Update Q1 2021

Jun 8, 2021

SITE DEVELOPMENT Site development for Phases 3 and 5 are nearing completion, now with 99.26% and 97.78% completion rates respectively. AMENITIES The Social Hall, Covered Court, and landscaping along the spine road and around the Clubhouse are starting this month. VECINO TURNOVERS To date, 118 lots have been turned over. Two households have also already… View Article

Read More

Seafront Residences Construction Updates Q4 2020

Feb 21, 2021

AboitizLand’s premier seaside community continues to welcome residents as the ongoing global situation has now made it possible to work-from-paradise. The property’s main signage is now installed while a few finishing touches for highway improvements are being worked on. Site development for Seafront Crest (Phase 2) is at 93% completion as of December 2020, with… View Article

Read More

The Villages at Lipa Construction Updates Q1 2023

Mar 31, 2023

Construction is in full swing Brook Village currently has 454 houses under construction and 80 completed houses. Meanwhile, Sierra Village has 367 houses under construction and 37 completed houses. Site Development Site development of Brook Village is at 98.31% completion, Sierra Village is at 97.22% completion, while Meadow Village is at 24.47% completion. Amenities Main… View Article

Read More
×