Construction Updates

Suggested Articles

Pristina North Residences Construction Updates Q4 2021

Jan 31, 2022

POST-TYPHOON ODETTE RECOVERY EFFORTS We are committed to ensuring that Pristina North vecinos and your properties are being well-taken care of especially during these trying times. Below are the site updates after Typhoon Odette hit the community, along with the rest of Visayas and Mindanao, last December: Water and power supply are fully restored as… View Article

Read More

Foressa Construction Updates Q1 2022

Jun 27, 2022

TURNOVERS 16 residential lots have been turned over as of Q1 2022.  SITE DEVELOPMENT Site development of Phase 1A is 100% complete.  CEBECO electrical distribution line setup is at 100%.  Streetlights to be installed in 2022 AMENITIES Foressa Lodge is under construction. Meanwhile, pool construction, parks and landscaping of other areas, town center and main… View Article

Read More

Foressa Mountain Town Construction Update Q1 2021

May 31, 2021

SITE DEVELOPMENT Site development for the Light Phase 1A is now complete with its main guardhouse fully constructed. AMENITIES Construction for the Foressa Lodge will begin in June 2021. VECINO TURNOVER Lot turnovers are rescheduled to begin in Q4 this year to allow the completion of necessary documents that were affected by the community quarantines… View Article

Read More
×