TURNOVERS Property turnovers are set to commence in Q4 2022. HOUSE CONSTRUCTION 26 house units have been constructed along with the model unit, while the construction of 135 house units are ongoing and in full swing.  AMENITIES The guardhouse and the boulevard landscape are completed. The clubhouse, basketball court, pool, and playground, are set to… View Article

Read More

Pristina North Residences Construction Updates Q2 2022

Sep 22, 2022

TURNOVERS 26 residential units have been turned over in Pristina North Residences Phase 2. HOUSE CONSTRUCTION IS 100% COMPLETED IN Pristina North Residences Phase 2. AMENITIES Street names and signages in Pristina North Residences 2 have been installed as of August 2022. Meanwhile, the construction of the perimeter fence is ongoing and set to be… View Article