Construction Updates

Suggested Articles

Ajoya Capas Construction Updates Q4 2020

Feb 21, 2021

Site Development Site development is now 100% complete. All roads within the property are passable. House Construction Construction is well underway for 65 units, with 53 more units targeted to begin within the year. Amenities The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021…. View Article

Read More

Amoa Construction Updates Q4 2023

Dec 31, 2023

House Construction 830 house units have been completed, while the construction of 139 house units are ongoing and in full swing. Site Development is fully completed for all launched enclaves. Amenities The 3 swimming pools, clubhouse, function area, grand lawn, and basketball courts have been completed. Turnovers 510 house units have been turned over along… View Article

Read More

Ajoya Pampanga Construction Updates Q4 2023

Dec 31, 2023

House Construction The model units and 105 houses have been completed, while the construction of 112 house units are ongoing and in full swing. Site development is nearing completion at 99%. Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Town Plaza is set to launch in Q1 2024…. View Article

Read More
×