7 house models are underway. Construction works will resume once enhanced community quarantine (ECQ) is lifted.
Site development for Sierra and Brook are at 5.81% and 5.64% completion rates, respectively.
Construction works on the spine road, drainage installation, and entrance lot earthworks will continue once ECQ is lifted.
For your family’s safety and comfort, guardhouse construction will begin in the second quarter of this year.
CONSTRUCTION Construction of the spine road to Malvar Entrance is now at 87% completion. SITE VISITS The Villages at Lipa remains open for site visits and model village viewing. Book a visit with your Property Specialist or Broker today. Rest assured that IATF’s guidelines are strictly implemented within its premises. VALUE APPRECIATION Lot value in… View Article
Read MoreSITE DEVELOPMENT Site development of Phase 1A is 100% complete, while Phase 1B is at 24.41% progress. AMENITIES The main pavilion construction is at a 34.93% completion rate. Construction on the town center, pool plaza and the major entrance signpost will begin by Q1 of 2023. VALUE APPRECIATION We would like to congratulate you on… View Article
Read MoreSite Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023. The Phase 1A Streetscape and main entry signage are currently… View Article
Read MoreP 0 / month