Constructions are in full swing
96 houses in Brook and 55 houses in Sierra are currently under construction. Turnovers to the vecinos are expected to begin Q3 2022.
Site Development
Brook is at 69.2% completed, while Sierra is at 72.4% completed.
The spine road in Malvar Exit still has 75 meters to go before completion.
Guardhouses
The main guardhouses of Lipa and Malvar entrances are complete already. Meanwhile, the in-village guardhouses for Brook and Sierra are under construction and set to be completed by Q3 2022
Value Appreciation
Lot value in our launched villages, Brook and Sierra, enjoy positive returns at 101% and 83% value appreciation respectively since they were launched in 2019.
Get updates and notifications through the AboitizLand Vecino App.
Download for free via the App Store or Play Store.
Help us innovate more ways to lead you home by sending your feedback HERE.
TURNOVERS Property turnovers are set to commence in Q1 2023. HOUSE CONSTRUCTION 55 house units have been constructed, while the construction of 107 house units are ongoing and in full swing. AMENITIES The guardhouse and the boulevard landscape are completed. The clubhouse, basketball court, pool, and playground are set to be completed in Q1 2023…. View Article
Read MoreConstruction is making steady headway 232 house and lot units have been completed while 164 houses are under construction. 3 villas have been completed while 5 villas are ongoing construction. Site Development is 100% complete Amenities The clubhouse, pool, boardwalk, jogging path at the lagoon, and other amenities are operational. The construction of the Crest… View Article
Read MoreHouse Construction The model units and 105 houses have been completed, while the construction of 112 house units are ongoing and in full swing. Site development is nearing completion at 99%. Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Town Plaza is set to launch in Q1 2024…. View Article
Read MoreP 0 / month