The Villages at Lipa Model Village will open in Q3 2020.
Construction of SA150 and SD103 (Sierra) plus SA80, SA65, and Townhouses (Brook) has resumed since ECQ and is in full swing.
Sierra Village – 16% completed;
Brook Village – 15% completed;
On-going site works include the entrance lot and the main road to the model village.
Guardhouse and entrance gate from JP Laurel to begin construction in August 2020.
SITE DEVELOPMENT Utilities are available in Crest for residential lot owners interested in building their beach home within the year. You may contact our Property Management Team or the Village Admin for submission of construction plans for approval. TURNOVERS Residential lot turnovers are fully underway and set to begin by Q4 of this year. VALUE APPRECIATION… View Article
Read MoreAboitizLand’s hyper-exclusive development in hometown Cebu continues to provide luxury living to the prime, private, and privileged. Site development is complete for Phases 1 and 2. On top of that, Phase 3 is currently at 97% while Phase 5A is at 96%. The parks, clubhouse, and major landscaping works are still on schedule to be… View Article
Read MoreSite development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year. House construction is scheduled to begin this first quarter. All five model units in the Model Village… View Article