Construction Updates

Suggested Articles

Ajoya Capas Construction Updates Q4 2023

Dec 31, 2023

House Construction The model units and 173 houses have been completed, while the construction of 25 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Town Plaza is set to launch in… View Article

Read More

Amoa Construction Updates Q3 2022

Nov 29, 2022

TURNOVERS 334 house units have been turned over along with 70 residential lots. HOUSE CONSTRUCTION 630 house units have been completed, while the construction of 319 house units are ongoing and in full swing.  AMENITIES The 3 swimming pools, as well as the clubhouse, function area, grand lawn, and basketball courts, have been completed. SALES… View Article

Read More

The Villages at Lipa Construction Updates Q1 2022

Jun 27, 2022

Constructions are in full swing 96 houses in Brook and 55 houses in Sierra are currently under construction. Turnovers to the vecinos are expected to begin Q3 2022. Site Development Brook is at 69.2% completed, while Sierra is at 72.4% completed. The spine road in Malvar Exit still has 75 meters to go before completion…. View Article

Read More
×