Turnovers expected to start in Q4 2022
Construction is in full swing
There are currently 320 houses under construction and 17 completed houses in Brook Village.
In Sierra Village, there are 26 completed houses and 207 houses currently under construction.
Site Development
Site development of Brook Village is at 92.24% completion, while Sierra Village is at 88.51% completion.
The spine road in Malvar Exit still has 75 meters to go before completion.
Amenities
Main Guardhouses at Lipa and Malvar have been completed.
The construction of in-village guardhouses for Sierra and Brook are ongoing and set to be completed by November 2022.
Value Appreciation
Lot value in our launched villages, Brook and Sierra, enjoy positive returns at 101% and 83% value appreciation respectively since they were launched in 2019.
Sales
There are 36 units in Sierra Village, while 48 units in Brook that are currently available.
Meadow Village is now open for selling!
Know someone who is looking for an investment in an exclusive community? Be one of our Referral Partners and earn Php 35,000 for every successful referral
ACCEPTANCE Acceptance for both residential lots and houses are set to commence in Q4 2021. Need assistance in funding your dream home in Ajoya Capas? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Construction works for 83 houses are currently ongoing in the launched phases with 36 houses already… View Article
Read MoreHouse Construction The model units and 159 houses have been completed, while the construction of 39 house units are ongoing and in full swing. Site Development is fully completed Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 61 units have been turned over…. View Article
Read MoreP 0 / month