Construction is in full swing
Brook Village currently has 469 houses under construction and 99 completed houses.
Meanwhile, Sierra Village has 346 houses under construction and 46 completed houses.
Site Development
Site development of Brook Village is at 98.97% completion, Sierra Village is at 98.05% completion, while Meadow Village is at 36.09% completion.
Amenities
Main Guardhouses at Lipa and Malvar have been completed as well as in-village guardhouses.
The construction of Sierra and Brook Clubhouse is currently underway, with a targeted completion by Q3 2024.
Turnover
House acceptance and lot only turnovers are ongoing.
1 house and lot, along with 9 residential lots, have been turned over.
Value Appreciation
Lot value in our launched villages, Brook and Sierra, enjoy positive returns at 118% and 90% value appreciation respectively since they were launched in 2019.
Sales
There are 53 units in Brook Village, 64 units in Sierra, and 59 units in Meadow Village that are available.
Know someone who is looking for an investment in an exclusive community?
Be one of our Referral Partners and earn up to Php 50,000* for every successful referral.
Talk to your Property Specialist or Broker today.
Terms and conditions apply.
A MASTER-PLANNED RESIDENTIAL COMMUNITY With its beautiful natural landscape of hills, vistas, and gentle breeze, this 60-hectare residential community is a collection of villages, forming smaller neighborhoods that allow more intimate and warm interaction and friendships. It is a place where neighbors are friends, where there are unbounded spaces and master-planned and life scale amenities… View Article
Read MoreHouse Construction 188 houses have been completed, while the construction of 45 house units are ongoing and in full swing. Site Development is fully completed Amenities The Clubhouse, Pool, Playground, Basketball Court, Gate Guardhouse, and Boulevard Landscape have been completed. The Town Plaza is set to be completed by Q4 2024. Turnovers 97 units have… View Article
Read MoreHouse Construction 830 house units have been completed, while the construction of 139 house units are ongoing and in full swing. Site Development is fully completed for all launched enclaves. Amenities The 3 swimming pools, clubhouse, function area, grand lawn, and basketball courts have been completed. Turnovers 510 house units have been turned over along… View Article
Read MoreP 0 / month