Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year.
House construction is scheduled to begin this first quarter. All five model units in the Model Village are also starting its interior design phase with a target completion date of April 2021.
The main entrance landing, with the main signage, guardhouse, and landscaping work, is nearing its completion.
The Outlets at Lipa and LIMA Exchange now house a total of 78 brands, all open daily for your shopping, dining, and business experience from 10AM to 9PM.
Hardware and home improvement store, Handyman, joined the list as the newest store in LIMA Exchange last January 2021.
House Construction 124 houses have been completed, while the construction of 98 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. The Town Plaza is set to be completed by Q4 2024. Turnovers 54… View Article
Read MoreTURNOVERS EXPECTED TO START IN Q3 2022. HOUSE CONSTRUCTION IN FULL SWING. There are currently 213 houses under construction and 18 completed houses in Brook Village. In Sierra Village, there are 9 completed houses and 72 houses currently under construction. SITE DEVELOPMENT Site development of Brook Village is at 80.32% completion, while Sierra Village is… View Article
Read MoreForessa Mountain Town is ready to welcome its first batch of turnovers beginning on November 2021. Need assistance in filing your home loan application? Read more about our home loan offerings and services here. SITE DEVELOPMENT The newest phase, Light B, with over 100 residential lots, is set to be launch in Q1 2022. CONSTRUCTION… View Article