Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year.
House construction is scheduled to begin this first quarter. All five model units in the Model Village are also starting its interior design phase with a target completion date of April 2021.
The main entrance landing, with the main signage, guardhouse, and landscaping work, is nearing its completion.
The Outlets at Lipa and LIMA Exchange now house a total of 78 brands, all open daily for your shopping, dining, and business experience from 10AM to 9PM.
Hardware and home improvement store, Handyman, joined the list as the newest store in LIMA Exchange last January 2021.
TURNOVERS A total of 149 houses and 41 residential lots have been successfully turned over as of Q3 2021. Due for a home loan take out? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION 427 houses have been constructed to date while the construction of 267 houses is in… View Article
Read MoreTurnovers are fully underway for residences. Seafront Residences has turned over 127 houses and lots and 52 residential lots. Turnover of Seafront Villas units will commence by Q4 2022. SITE DEVELOPMENT IS 100% COMPLETE Seafront Villas Soon To Be Ready For Turnovers With 191 houses completed, 6 villa buildings and the construction of 208 other… View Article