Site development for Sierra Village is at 24% completion, while Brook Village is at 25%. The spine road from the Entrance Landing along JP Laurel Highway is set to be accessible within the first quarter of this year.
House construction is scheduled to begin this first quarter. All five model units in the Model Village are also starting its interior design phase with a target completion date of April 2021.
The main entrance landing, with the main signage, guardhouse, and landscaping work, is nearing its completion.
The Outlets at Lipa and LIMA Exchange now house a total of 78 brands, all open daily for your shopping, dining, and business experience from 10AM to 9PM.
Hardware and home improvement store, Handyman, joined the list as the newest store in LIMA Exchange last January 2021.
SITE DEVELOPMENT Site development is at 54%, with Phase 1 (64 hectares) set to be completed by November 2021. HOUSE CONSTRUCTION House construction began with 20 units in January. Construction of the model units is also in full swing, targeted to be completed by Q4 this year. AMENITIES Main amenities are targeted to be completed… View Article
Read MoreTHE VILLAGES AT LIPA IS HIGHLY COMMENDED IN SOUTHERN LUZON The Villages at Lipa was Highly Commended at the Best Housing Development in Luzon category at the 2021 Philippine Property Awards spearheaded by Singapore-based PropertyGuru Property Awards. This recognition is given to celebrate and honor exemplary property developers in the country. CONSTRUCTION IN BROOK AND… View Article