Construction Updates

Suggested Articles

Foressa Mountain Town Construction Updates Q3 2023

Oct 25, 2023

Site Development The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023. Amenities The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023. The Phase 1A Streetscape and main entry signage are currently… View Article

Read More

The Villages at Lipa Construction Updates Q1 2022

Jun 27, 2022

Constructions are in full swing 96 houses in Brook and 55 houses in Sierra are currently under construction. Turnovers to the vecinos are expected to begin Q3 2022. Site Development Brook is at 69.2% completed, while Sierra is at 72.4% completed. The spine road in Malvar Exit still has 75 meters to go before completion…. View Article

Read More

Foressa Mountain Town Construction Updates Q3 2022

Dec 1, 2022

SITE DEVELOPMENT Site development of Phase 1A is 100% complete, while Phase 1B is at 24.41% progress. AMENITIES The main pavilion construction is at a 34.93% completion rate. Construction on the town center, pool plaza and the major entrance signpost will begin by Q1 of 2023. VALUE APPRECIATION We would like to congratulate you on… View Article

Read More
×