Construction of the spine road to Malvar Entrance is now at 87% completion.
The Villages at Lipa remains open for site visits and model village viewing.
Book a visit with your Property Specialist or Broker today.
Rest assured that IATF’s guidelines are strictly implemented within its premises.
Lot value in our launched villages, Brook and Sierra, enjoy positive growth at 52.29% and 52.54 respectively since they were launched in 2019.
Get updates and notifications through the AboitizLand Vecino App. Download for free via the App Store or Play Store.
We would like to hear your thoughts, suggestions, or concerns about your recent transaction with us. Click HERE to share your feedback.
House Construction The model units and 90 houses have been completed, while the construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Turnovers 9 units have been turned over. Turnover Offices… View Article
Read MoreHouse Construction The model units and 173 houses have been completed, while the construction of 25 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Town Plaza is set to launch in… View Article
Read MoreACCEPTANCE Acceptance for both residential lots and houses are set to commence in Q4 2021. Need assistance in funding your dream home in Ajoya Capas? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Construction works for 83 houses are currently ongoing in the launched phases with 36 houses already… View Article