Ajoya Pampanga Construction Updates Q1 2023

Mar 31, 2023

House Construction 55 house units have been completed as well as the model units which has been launched. The construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99%. Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse and Boulevard Landscape have been completed. Turnovers 3 units… View Article

Read More

Ajoya Cabanatuan Construction Updates Q4 2020

Feb 21, 2021

Site Development Site development is nearing its completion at 85% with a target completion date within the first quarter of this year. House Construction Construction is well underway for 31 units, with 98 more units targeted to begin with the year. Vecino Turnovers Turnovers are set to start in Q3 of this year. Sales A… View Article

Read More
×