Site Development Land development of Phase 1A is 100% complete, while Phase 1B is at 65% progress ahead of schedule. Amenities Target completion for Main Pavilion by Q2 2023, Main Entry Signage by 3Q 2023, and Outdoor Camping Grounds by 4Q 2023. Turnover 89 lots have been turned over to vecinos. Value Appreciation Residential lot… View Article

Read More

Ajoya Pampanga Construction Updates Q3 2022

Dec 1, 2022

TURNOVERS Property turnovers are set to commence in Q4 2022. HOUSE CONSTRUCTION 26 house units have been constructed along with the model unit, while the construction of 135 house units are ongoing and in full swing.  AMENITIES The guardhouse and the boulevard landscape are completed. The clubhouse, basketball court, pool, and playground, are set to… View Article

Read More

The Villages at Lipa Construction Updates Q4 2022

Dec 31, 2022

Construction is in full swing Brook Village currently has 267 houses under construction and 80 completed houses. Meanwhile, Sierra Village has 203 houses under construction and 37 completed houses. Site Development Site development of Brook Village is at 96.06% completion, Sierra Village is at 96.09% completion, while Meadow Village is at 17.21% completion. Amenities Main… View Article