Construction Updates

Suggested Articles

Ajoya Capas Construction Updates Q4 2020

Feb 21, 2021

Site Development Site development is now 100% complete. All roads within the property are passable. House Construction Construction is well underway for 65 units, with 53 more units targeted to begin within the year. Amenities The clubhouse, court, pool pavilion, and pool facilities are all under construction with a target completion date of Q4 2021…. View Article

Read More

Foressa Mountain Town Construction Updates Q1 2023

Mar 31, 2023

Site Development Land development of Phase 1A is 100% complete, while Phase 1B is at 65% progress ahead of schedule. Amenities Target completion for Main Pavilion by Q2 2023, Main Entry Signage by 3Q 2023, and Outdoor Camping Grounds by 4Q 2023. Turnover 89 lots have been turned over to vecinos. Value Appreciation Residential lot… View Article

Read More

Ajoya Pampanga Construction Updates Q2 2021

Sep 16, 2021

SITE DEVELOPMENT Site development is now at 73% with Phase 1A set to be finished by Q3 of this year. HOUSE CONSTRUCTION Construction of 40 new units are now in full swing. AMENITIES The landscaping work along the Main Boulevard is set to be completed by December of this year while main amenities including Parks… View Article

Read More
×