Construction Updates

Suggested Articles

The Villages at Lipa Construction Updates Q3 2022

Nov 29, 2022

Turnovers expected to start in Q4 2022 Construction is in full swing There are currently 320 houses under construction and 17 completed houses in Brook Village.  In Sierra Village, there are 26 completed houses and 207 houses currently under construction. Site Development Site development of Brook Village is at 92.24% completion, while Sierra Village is… View Article

Read More

Amoa Construction Updates Q1 2024

Mar 31, 2024

House Construction 888 house units have been completed, while the construction of 81 house units are ongoing and in full swing. Site Development is fully completed for all launched enclaves. Amenities The 3 Swimming Pools, Clubhouse, Function Area, Grand Lawn, and Basketball Courts have been completed. Turnovers 550 house units have been turned over along… View Article

Read More
×