TURNOVERS EXPECTED TO START IN Q3 2022.
HOUSE CONSTRUCTION IN FULL SWING.
There are currently 213 houses under construction and 18 completed houses in Brook Village. In Sierra Village, there are 9 completed houses and 72 houses currently under construction.
SITE DEVELOPMENT
Site development of Brook Village is at 80.32% completion, while Sierra Village is at 81.55% completion.
The spine road in Malvar Exit still has 75 meters to go before completion.
GUARDHOUSES
Lipa and Malvar’s primary guardhouses are now operational. Meanwhile, the in-village guardhouses for Brook and Sierra are under construction and set to be completed by Q3 2022.
VALUE APPRECIATION
Lot value in our launched villages, Brook and Sierra, enjoy positive returns at 101% and 83% value appreciation respectively since they were launched in 2019.
SALES
There are 8 remaining lots in Sierra Village that are currently available.
Know someone who is looking for an investment in an exclusive community? Be one of our Referral Partners and earn Php 35,000 for every successful referral. http://bit.ly/vecinoreferral
Help us innovate more ways to lead you home by sending your feedback HERE.
HOUSE CONSTRUCTION 30 houses are completed while construction for 106 new units is in full swing. The model units also remain open for vecinos who want to visit the site. Our Property Specialists and/or Accredited Brokers will be able to assist you in scheduling visits. AMENITIES The Clubhouse, Court, and Pool Facilities are all under… View Article
Read MoreSITE DEVELOPMENT While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year. HOUSE CONSTRUCTION There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022. The model units also remain… View Article