TURNOVERS EXPECTED TO START IN Q3 2022.
HOUSE CONSTRUCTION IN FULL SWING.
There are currently 213 houses under construction and 18 completed houses in Brook Village. In Sierra Village, there are 9 completed houses and 72 houses currently under construction.
SITE DEVELOPMENT
Site development of Brook Village is at 80.32% completion, while Sierra Village is at 81.55% completion.
The spine road in Malvar Exit still has 75 meters to go before completion.
GUARDHOUSES
Lipa and Malvar’s primary guardhouses are now operational. Meanwhile, the in-village guardhouses for Brook and Sierra are under construction and set to be completed by Q3 2022.
VALUE APPRECIATION
Lot value in our launched villages, Brook and Sierra, enjoy positive returns at 101% and 83% value appreciation respectively since they were launched in 2019.
SALES
There are 8 remaining lots in Sierra Village that are currently available.
Know someone who is looking for an investment in an exclusive community? Be one of our Referral Partners and earn Php 35,000 for every successful referral. http://bit.ly/vecinoreferral
Help us innovate more ways to lead you home by sending your feedback HERE.
AboitizLand’s hyper-exclusive development in hometown Cebu continues to provide luxury living to the prime, private, and privileged. Site development is complete for Phases 1 and 2. On top of that, Phase 3 is currently at 97% while Phase 5A is at 96%. The parks, clubhouse, and major landscaping works are still on schedule to be… View Article
Read MoreHouse Construction 805 house units have been completed, while the construction of 159 house units are ongoing and in full swing. Site Development is fully completed for all launched enclaves. Amenities The 3 swimming pools, clubhouse, function area, grand lawn, and basketball courts have been completed. Turnovers 450 house units have been turned over along… View Article
Read MoreP 0 / month