AboitizLand’s hyper-exclusive development in hometown Cebu continues to provide luxury living to the prime, private, and privileged.
Site development is complete for Phases 1 and 2. On top of that, Phase 3 is currently at 97% while Phase 5A is at 96%.
The parks, clubhouse, and major landscaping works are still on schedule to be completed within 2021.
To date, 117 lots have been turned over.
TURNOVERS EXPECTED TO START IN Q3 2022. HOUSE CONSTRUCTION IN FULL SWING. There are currently 213 houses under construction and 18 completed houses in Brook Village. In Sierra Village, there are 9 completed houses and 72 houses currently under construction. SITE DEVELOPMENT Site development of Brook Village is at 80.32% completion, while Sierra Village is… View Article
Read MoreSite Development Site development is nearing its completion at 85% with a target completion date within the first quarter of this year. House Construction Construction is well underway for 31 units, with 98 more units targeted to begin with the year. Vecino Turnovers Turnovers are set to start in Q3 of this year. Sales A… View Article
Read MoreSITE DEVELOPMENT While land development is now complete, the perimeter fence is set to be fully installed by Q3 this year. HOUSE CONSTRUCTION There are 11 houses at a 95% completion rate and 84 more houses being constructed in full swing. Shophouses are targeted to be completed by Q1 2022. The model units also remain… View Article
Read MoreP 0 / month