Wrapping up the site development for the Light Phase, its guardhouse is set to be completed within the first quarter of this year.
The Foressa Lodge receives its green light to start construction in the first half of the year.
The sanctuary you have long deserved is here. Turnovers are scheduled to begin in the third quarter of 2021.
The current lot price has increased to Php12,360/sqm to date, from Php9,520/sqm when it was first launched in 2017.
TURNOVERS 3 house units have been turned over. HOUSE CONSTRUCTION 137 houses have been completed, while the construction of 100 house units are ongoing and in full swing. AMENITIES The guardhouse, gate, and boulevard landscape have been completed, while the basketball court and clubhouse are set to be completed by Q1 2023. SALES 100 units… View Article
Read MoreTURNOVERS 34 house units have been turned over. HOUSE CONSTRUCTION 141 houses have been constructed along with the model units, while the construction of 29 house units are ongoing and in full swing. AMENITIES The gate, guardhouse, pool, clubhouse, boulevard landscape, playground, and basketball court have been completed. SALES 93 units are currently available. Know… View Article
Read MoreModel Village Construction 7 house models are underway. Construction works will resume once enhanced community quarantine (ECQ) is lifted. Site Development Site development for Sierra and Brook are at 5.81% and 5.64% completion rates, respectively. Construction works on the spine road, drainage installation, and entrance lot earthworks will continue once ECQ is lifted. Amenities For… View Article